What are the estimated timelines?

PHASE 1: THE DEVELOPER’S TURN (WE ARE HERE πŸ“)

PHASE 2: THE SUBMISSION (THE REAL CLOCK STARTS)

  • Late Q1 2026 (Feb/March): Application Submitted. Hourigan Planning sends the final documents to Lichfield District Council.
  • Validation: The Council checks the paperwork. Once “Validated,” the application appears on the Lichfield Council website with a Planning Reference Number (e.g., 26/00123/OUTM).

PHASE 3: THE PUBLIC VOTE (THE “STATUTORY” WINDOW)

  • March/April 2026 (Est.): Official Council Consultation. ⚠️ CRITICAL MOMENT: This is the 21-day legal window where you must submit your “Formal Objection” to the Council. (Note: Your email to the developer in Phase 1 does NOT count as a formal objection to the Council. You must do it again here.)

PHASE 4: THE REVIEW

  • Spring/Summer 2026: Officer Assessment. Planning Officers review all objections, consult highways/ecology experts, and negotiate with the developer.
  • Screening Opinion: The Council decides if a full Environmental Impact Assessment (EIA) is needed (as discussed earlier).

PHASE 5: THE DECISION

  • Late 2026:Planning Committee Meeting. Because this is a large development (225 homes), it will likely go to a vote by elected Councillors at a public meeting.
    • We can speak at this meeting.
    • Councillors vote to Approve or Refuse.